How to commence repair works of the apartment?

The initial stage of typically the repair of old apartments is the destruction and dismantling first of just about all of the dilapidated walls and partition wall space, removing the wall structure and ceiling layer. This stage will be one of typically the most “dirty” phases in the repair.

1 more being among the most essential and “dusty” performs is the windows block replacement. You need to do this first of all due to the fact dirt and dust particles will be unallowable in the course of following stages plus it is forbidden at all to be able to open windows in the course of painting and wallpapers works (large droplets of the heat and moisture are usually unallowable). After mounting windows and windowsills it is essential to pack them immediately in polyethylene film and to cover windowsills inside addition with the fiberboard (in in an attempt to avoid scratches).

These period is wiring. Electrical wiring can be set up in walls or perhaps along the ground. Wiring is made inside the pipes to ensure electric safety and enhance reliability. The pipe protects wiring through external damages in addition to allows to substitute the wire totally without breaking wall space and floor simply by inserting the brand new wire instead of the old one.

House Painting comes after the wiring. The frequent mistake during the simultaneous executing of such works occurs when staff forget to lay out among the cabling and house painters have already drunk and smoothed out the wall. As a result, additional works are necessary to be able to seal chases on the finished wall. The particular places of the feed switch and wall outlet location and the number should be thought-out in advance. The structure of power wiring is usually included to the design project.

Down the road the method must be ready to service in circumstance of failures. Within addition to typically the wirings, the phone cable connection and the TELEVISION cable are laid out. The power cable really should not be laid out there near the phone and antenna cables to avoid noise pickup and interference. One of the most peculiar moment is laying out there the TV wire. In order to be able to make two (or three) TV makes its presence felt the apartment the 2nd cable is usually simply “firmly soldered” in parallel, so the cable resistance is lowered. Because a result, the particular image quality is deteriorated, many programs can’t be received plus etc. In order to avoid these kinds of situation it is usually necessary to invite a specialist together with special equipment. This individual will gauge the transmission level of the particular each TV-feeder in addition to install TV-amplifiers or even TV-filters.

Painting is among the most long-term process, this is why it is performed simultaneously in almost all premises, when it is feasible. Delays are associated with the technologies. Each applied level of the plastsorter (or filling in finishing) must dry completely ahead of the job will continue.

Performs in sanitary plans and the kitchen begin simultaneously along with house painting. It is better to fulfill alleged “dirty” works within the first location and simultaneously. Inside accordance with the master plan of the sanitary technician location welding, wall chasing and pipe run usually are conducted. Steam radiator admissions are prepared, taps and mounting brackets are mounted, nevertheless radiators aren’t mounted.

Then works in sanitary arrangements usually are conducted according to the plan. The bath is usually mounted, then surfaces are smoothed away and the tile is laid about walls. The subsequent stage is assembling ceiling and putting tiles on typically the floor. And in last other hygienic devices, mixers plus accessories are mounted.

After wiring, installation of rosette plates and terminal containers the voltage is checked in most stage. Ends of electrical wiring are insulated in addition to laid out into rosette plates. Electrical sockets and breakers are not installed during this stage in purchase to save their particular surface appearance. The finish puttying associated with walls is conducted simultaneously. The technologically exact control of drying out of the layer of the plaster (filling) is carried out by drymeter. It is the special instrument that will measures moisture associated with the material.

The following stage is typically the process of fill. Fill up could be made with different materials — from usual masonry cement-sand mixture to be able to self-aligning floors. Typically the advantage of the simple mixture is its cheapness, the particular disadvantage is of which such mixture is much harder lined up at the degree and the final dry time of such fill is usually 40 days, only then the subsequent stage of typically the work with floor can be conducted, we. e. the period is too long. Self-leveling self-aligning floors are much more expensive, but more technological. Aiming occurs almost “automatically” i. e. fluid solution of blend is poured away, then it operates and you obtain the horizontal area. The final dried out time is two weeks i. e. you could have significant time economic climate. The system “warm floor” is set up into the fill. In case the so-called “wet processes” are inapplicable the technology of the dry aiming (the fill technology) is used bases for floors together with adjustable floor battens are mounted.

Following fill door containers and door usually are installed. Duraflex of doors must take directly into the account thickness of future floor covering. After installation the doorway can be obtained off its knobs and removed till the end of repair or packed into polyethylene film to protect from damages. Simultaneously threshold can be painted in addition to the tile may be laid in that premises where it absolutely was planned. The tile must be set within the absolutely dry out overlay.

Finishing regarding the floor mounting depends on the particular planned covering. In most cases (if finish covering is not really the tile) fill is covered by bitumen mastic and plywood sheets are usually laid. They are usually fixed to the floor by self-tapping anchoring screws. One plywood sheet is fixed simply by 30-50 self-tapping anchoring screws to provide the close fixing of plywood and long-term service of the flooring without squeak in addition to bulging. The plywood gives the added heat- and acoustic insulation. After increasing of the hdf is completed, wallpaper with regard to painting can become pasted on walls.

In premises where finish covering of the floor is usually laminated flooring or parquet hoard, the normal wallpapers are pasted (not for painting) in the first place. Then the floor covering is attached.

If finish masking in the floor will be the block parquet, the parquet will be laid to start with, and then it is scraped and covered simply by one layer associated with lacquer. After this specific the ordinary wall-papers are pasted as well as the parquet is included in the rest levels of lacquer (depending on the quality associated with the parquet in addition to lacquer). The mentioned consequence is linked only with this kind of scrambling process any time the great sum of dust is usually created. Regardless of the fact that good floor grinders usually are equipped with the particular vacuum cleaner, the sufficient amount of dust is precipitated on surrounding subject matter including walls. Dirt is very acerbic and is badly washed off. That is why so as not to harm wallpapers, they are pasted after trying and in order the parquet tend not to absorb the excess moisture it is usually covered by the main one layer of lacquer before wallpaper pasting.

After this typically the main works can be considered to be finished. It is left just to install the plinths, decorative elements, breakers and sockets, curtain holders, to suspend doors, plant-bands in addition to others.

To conclude it is necessary in order to note that the sequence of works was listed inside general and can change depending on the particular situation – the number of bedrooms in premise, your resources, peculiarities associated with the construction of the multilevel property. It is centered on sound judgment in addition to every person effective at analysis can separately create such a new sequence.

Leave a Comment